Allai Khwar Hydropower Project

Location

On Allai Khwar, Left Tributary of Indus River near Besham in District Battagram, Khyber Pakhtunkhwa

Salient Features

  • Dam Height
  • Length of Headrace
  • Installed Capacity
  • Annual Energy
  • Gross Head
  • Objectives
  • EIRR

32.50 m

2366 m

121 MW

463 GWh

697 m

To Generate Electricity

23.97%

Consultants

HHH Consultants, NDC, LAHMEYER, BARQAAB, BAK, PES, EGC, RC, IDC & DMC

Contractor

DEC Astron, VA Tech

Donor Agency

Government of Pakistan

Execution by

WAPDA

Date of Commencement     

June 2003

Date of Completion 

March 2013                          

Financial Status (Rs. Million)

Local

FEC

F/LOAN

Total

Original PC-I Cost

5,124.284

3,453.540

-

8,577.824

Revised PC-I Cost

7,312.687

6,522.261

-

13,834.948

Expenditure upto 30.06.2014

6,414.481

5,554.621

3,700.657

15,669.759

 

  • Physical Progress Completed
  • Financial Progress*113.26% against 100%

*2nd Revise PC-I amounting to Rs. 16,221.844 Million submitted to Ministry of Water & Power on 19.02.2013 and forwarded to Planning Commission on 22.10.2013. Rationalized / updated cost (Rs.17234.300 million) was intimated to Ministry of Water & Power on 06, Feb. 2014 which was forwarded to Ministry of Planning Development & Reforms on 21.05.2014.

  • Commercial operation started w.e.f. 25 March, 2013.
  • Upto date Hydel Generation = 882.903 MKW/h.
Read 28541 times