Jinnah Hydel Power Station

JINNAH HYDROPOWER PROJECT

 Location The Project is located on the right side of existing Jinnah Barrage, 5 km from Kalabagh town in District Mianwali and 234 km from Islamabad.
Salient Features
Installed Capacity 96 MW
Mean Annual Energy 688 GWh
Design Discharge 2400 m3/sec
Gross Head 4.88 m
No. & Type of Turbine 8-Pit Type
Turn Key Cost 128 Million US$
Implementation Period 4 years
Execution by WAPDA
Supervision Consultants JV of ACE,NESPAK,NDC,MWH,DMC&EASEPAK(demobilized)
Commencement Date 18th February, 2006
Completion Date Substationally completed on 31.10.2013
Financial Status Local (Rs. Millions) FEC (Rs. Millions) Total (Rs. Millions)
Original PC-I Cost 6938.579 6608.221 13546.800

 

Status

Physical Progress:                             99.97%

 

The Project Status is as under:

UNIT NO.1

The Unit is under commercial operation since 31.03.2012.

UNIT NO.2

The Unit is under commercial operation since 08.10.2012.

UNIT NO.3

The Unit is under commercial operation since 16.08.2012.

UNIT NO.4

The Unit is under commercial operation since 30.04.2013

UNIT NO.5

The Unit is under commercial operation since 26.04.2013.

UNIT NO.6

The Unit is under commercial operation since 14.10.2013.

UNIT NO.7

The Unit is under commercial operation since 14.10.2013.

UNIT NO.8

The Unit is under commercial operation since 26.07.2013.

                                               

O&M Staff Colony

The construction work of O&M colony at Jinnah Hydropower Project is under progress. The overall physical progress is 77.25%.

 

Incharge of the Project

Muhammad Rafiq

General Manager (Hydro) Planning,

WAPDA, Sunny View, Lahore

Contact No. 0092-42-99202717

Cell No.       0300-5604910

Read 40405 times