Khan Khwar Hydropower Project

Location

Khan Khwar River, a tributary of Indus River in District Shangla (Khyber Pakhtunkhwa)

Salient Features

  • Dam Height
    • Length of Headrace Tunnel
    • Gross Head
    • Objectives
    • Installed Capacity
    • Annual Energy
    • EIRR

30 m

4540 m

257 m

To Generate Electricity

72 MW

306 GWh

29.56%

Scope of Work

The project envisages installation of 72 MW Hydropower plant alongwith allied transmission and grid facility. The plant will generate 306 GWh/annum of electricity.

Consultants

HHH Consultants, NDC, LAHMEYER, BARQAAB, BAK, PES, EGC, RC, IDC & DMC

Contractor

CWH-HE, DEC

Execution by

WAPDA

Date of Commencement     

June 2003

Date of Completion 

March 2012                          

Financial Status (Rs. Million)

Local

FEC

Total

Original PC-I Cost

2,718.607

2,644.098

5,362.705

Revised PC-I Cost

4,573.688

3,727.791

8,301.479

Expenditure upto 30.10.2013

5,854.724

4,340.641

10,195.365

 

 

  • Physical Progress Completed
  • Financial Progress*122.81% against 100%

* 2nd revise PC-I cleared by CDWP at cost of Rs. 10,732.788 Million on 18.06.2012.

 

  • Commercial operation started w.e.f. Nov 08, 2010.
  • Upto date Hydel Generation = = 948.528 MKWh.

 

                              

                   