Neelum Jhelum HydroElectric Project (NJHEP)

Neelum Jhelum HydroElectric Project (NJHEP)

Location: The Project diverts Neelum river water through tunnels at Nauseri about 41 km upstream of Muzaffarabad and out falling in Jhelum River near Chatter Kalas in AJ&K, where the powerhouse is located.

Salient Features

 Dam Type

Composite Dam (Gravity+Rockfill)                  

nj

Dam Height / Length

60 / 160 meters

Tunnel Length
  • Twin Tunnel, Length 19.6 km each
  • (Total 39.2 km)
  • X-section Area varies from 52m2 to 58m2
  • Single Tunnel, Length 8.94 km
  • X-section Area 104 m2
  • Tailrace Tunnel, Length 3.55 km
  • X-section Area 99 m2
  • Diversion Tunnel 0.5 km
  • Access / Misc. tunneling 16 km
Installed Capacity 969 MW
Gross Head

420 m

Design Discharge 280 cumecs
 No. of Units 4 Turbines of 242.25 MW each
Annual Energy

5,150 GWh  (5.15 billion units annually)

Execution by

WAPDA

Consultants

M/s NJC JV, MWH USA, NORPLAN A.S, Norway, NESPAK, ACE, & NDC

Contractor

CGGC-CMEC, Consortium of China

Commencement Date

January 2008

Completion Date

13th April 2018 (1st Unit)                                        

Financial Status (Rs. Million)

Local

Foreign

Total

Revised PC-I Cost (23.05.2018)

270,427.860
236,380.150
506,808.610
PSDP Allocation 2022-2023
12,083.000
-
12,083.000

 Status

  • All Units have been synchronized as follows:-
  • Unit No. 4 synchronized on April 09, 2018
  • Unit No. 3 synchronized on April 22, 2018
  • Unit No. 2 synchronized on May 29, 2018
  • Unit No. 1 synchronized on August 13, 2018

 Tailrace Tunnel Blockage and Powerhouse Shutdown
• Excessive leakage/seepage was observed in the powerhouse from 04.07.2022 to 06.07.2022. In order to keep find-out the cause of excessive seepages of water, joint visits and inspections of the powerhouse by the NJHPC team and Project Consultants were carried out on 05.07.2022. It was found that the downstream water head was increased from 600 meters to 616 meters.
• After dewatering the lower section of the tailrace tunnel, a team visited the tunnel on 31.07.2022 up to the collapsed area & observed complete blockage of the tunnel at Chainage 0+293.
• Negotiations with the sitting Contractor M/s CGGC continued to finalize contract conditions and estimated cost of additional works for restoring the tailrace tunnel.

Physical Progress                    99.86%

Neelum Jhelum Videos

• Overall Generated Units are 18,286.383 MkWh.


In charge of the Project
Muhammad Arfan Miana
Managing Director / Chief Executive Officer
Neelum Jhelum Hydropower Project
Contact No. 0092-5822922314