Golen Gol Hydropower Project

Golen Gol Hydropower Project

Location
On Golen Gol River, a major tributary of Mastuj River in the District Chitral of KP.
Salient Features
  • Weir Height
12 m  
  • Head Race Tunnel Length
3.8 km
  • Gross Head
436 m
  • Design Discharge
30 m3/sec
  • Installed Capacity
108 MW 
  • Objectives
To Generate Electricity
  • Annual Energy
442 GWh  

Execution by

WAPDA
Consultants JV of M/s Fichtner Germany (Lead Firm), M/s PES Pakistan, M/s BAK Pakistan & M/s DMC Pakistan
Contractor

Lot-2    M/s SAMBU SARCO JV

Lot-3.1 M/s SAMBU SARCO JV

Lot-3.2 M/s Andritz Consortium, Austria

Lot-4 (Package-I)  M/s NETRACON-NEIE/HOLLEY,                           

          (Package-II) M/s NETRACON Consortium

Commencement Date February 2011                                                                             
Completion Date

January 2018

Financial Status (Rs. Million) Local Foreign Total
1ST Revised PC-I Cost (30.09.2016) 18,397.288 10,679.885 29,077.173
PSDP Allocation 2022-2023 2,618.000 200.000 2,818.000
Status:

Lot-1 O&M Colony

(Contract Cost Rs. 149.726 Million) through PSDP

 

 

 

 

Overall Physical Progress 100%.

 

Unit-1 was commissioned on 23.01.2018.

All compulsory tests have been completed and currently, Unit-1 is in operation and generating 2.75 MW

Unit-2 & 3 are in commercial operation w.e.f 15.09.2020

Lot-2 Civil Works (Contract Cost Rs.7,521 Million) financed by Saudi Fund for Development (SFD)

Lot-3.1 Civil Works of Powerhouse

(Contract Cost Rs.1,912 Million) financed by Kuwait Fund for Development (KFD)

Lot-3.2 E&M Works (Contract Cost Rs.5,650 Million) financed by Kuwait Fund for Development (KFD)

Lot-4 Transmission Line (Contract Cost Rs.4,897 Million) financed by OPEC Fund for International Development (OFID)

Package-I Cost Rs. 3,441 Million

Package-II Cost Rs. 1,456 Million

  • Physical Progress              Completed
 
In charge of the Project
 

Engr. Altaf Qadir

CE/PD Golen Gol HPP

Contact No. 0092-943-477103

 